Case study

Arup HQ

Central Leeds

Project: Combined M&E – CAT B Fit Out
Contract: Design & Build
Sector: Comerical Office Space
Client: Arup
Main contractor: Overbury
Contract value: £2M
Duration: 35 Weeks
Completed: 2023
See more below

CP Hood were contracted to complete a Category B fit-out of the Arup main building in central Leeds.

Minor modifications were required to the existing 4 pipe fan coil system. All service were exposed meaning close attention to detail was taken when positioning kit and subsequently installing at site level.

Works provided included:

  • Task and feature lighting
  • Power
  • Containment
  • Audio Visual
  • Data