Case study

Belvedere
Academy

Liverpool

Project: Combined M&E – Boiler Upgrades
Contract: Design & Build
Sector: Public Sector Decarbonisation
Client: CCO Building Consultancy
Main contractor: Direct
Contract value: £500K
Duration: 8 Weeks
Completed: 2021
See more below

As part of public sector decarbonisation 1 (PSDS 1), we were instructed to assist with supporting the bid for the decarbonisation work.

Works included the upgrade of 3 boiler rooms across the sign from old inefficient kit to the new more modern high efficient plant and controls.

All lighting, power, mechanical and controls work was carried out by CP Hood including al builders work and making good.

The work was carried out during the 6 week summer holidays with all boiler rooms running simultaneously.

All case studies