Bio City Nottingham Chiller Replacement

Nottingham

Project: Combined M&E
Contract: Design & Build
Sector: Plantrooms & Chiller Replacements
Client: Pioneer
Main contractor: J Mills
Contract value: £750K
Duration: 20 Weeks
Completed: 2022
See more below

We were contracted to undertake a short 8 week programme of works to replace 3 existing air cooled liquid chillers with the new, modern digital modulating scroll compressor chillers.

The works also included:

  • Pipework upgrades
  • New electrical mains
  • New building management systems