Case study

Bio City Glasgow Boiler House

Galsgow

Project: Combined M&E
Contract: Design & Build
Sector: Plantrooms & Chiller Replacements
Client: Pioneer
Main contractor: Direct
Contract value: £600K
Duration: 25 Weeks
Completed: 2023
See more below

Bio City Glasgow is a 20-acre biotech incubator with an assortment of  contemporary offices and laboratories providing cutting edge pharmaceutical and biotherapeutics research.

We were contracted to replace old, inefficient gas fired boilers with new, utilising existing pipework.

Our energy team had advised that they be replaced and offered a payback calculation meaning that the boilers had paid for themselves within four years.